Stairs / Projects / Hedda Andersson Gymnasiet

Lund, Sweden · Upper secondary school

Twelve steel stairs for a school that never stops moving

Twelve steel stairs, about 67 tonnes of structural steel, for the Hedda Andersson upper secondary school in Lund, Sweden: closed straight stairs and spiral stairs, lifted, aligned and welded on site.

Three-storey spiral stair clad in vertical timber slats in the school atrium, Lund

Project facts

Location
Lund, Sweden
Building
Upper secondary school
Stairs
12 steel stairs, straight and spiral
Steel
About 67 tonnes
Balustrade
8 mm flat steel, prepared for wood cladding
Our scope
Engineering, fabrication and installation of the steel structure
Built
2021–2022

The challenge

Public buildings need stairs that look light and carry heavy daily use. Here the stairs run through the building up to the 13th floor, prepared for wood cladding, insulation and poured concrete steps.

Our solution

That balance is engineering, not decoration: welded steel structures with 8 mm flat steel balustrades ready for wood cladding, delivered from Riga and installed by our own crew. The spiral stairs in the atrium were then painted and clad in vertical oak slats. The oak cladding was supplied and fitted by others – everything in steel we engineered, fabricated, delivered and installed ourselves.