Stair regulations in Germany

The numbers that matter when you design a stair or balustrade in Germany, from DIN 18065 + LBO / MBO § 38.

· Source status: Official texts and published guidance

Requirements

Rail height on stairs900 mm (drop 1–12 m); 1100 mm (drop over 12 m)
Rail height on landings and balconiesThe same; 1000 mm in workplaces (e.g. Hesse)
Max opening in guarding≤ 120 mm in at least one direction (e.g. Berlin § 38); Baden-Württemberg: horizontal gaps ≤ 20 mm up to 600 mm height
Gap between open treads≤ 120 mm (DIN 18065 for non-residential buildings; some LBO also for housing)
ClimbabilityClimbing must be made difficult (vertical bars, a closed panel up to 700 mm, etc.)
RiseBuildings with up to 2 dwellings 140–200 mm; other buildings 140–190 mm
GoingUp to 2 dwellings 230–370 mm; other buildings 260–370 mm
Stair widthUp to 2 dwellings 800 mm; other buildings 1000 mm
Headroom2000 mm
Handrail extension≥ 300 mm horizontal (DIN 18040, barrier-free)
LandingsAfter at most 18 risers (DIN 18065; not in buildings with up to 2 dwellings)
Marking of first and last stepDIN 18040 (barrier-free): 40–50 mm strip at the tread nosing, 10–20 mm on the riser; at least the first and last step
Spiral and curved stairsWinders: going ≥ 50 mm at the inner boundary (dwellings)
NotesSide gap to the wall or guarding ≤ 60 mm. Each federal state has its own building code (LBO) – check the one that applies.

Summary for designers, last checked November 2026. Always confirm against the current official text and with the local building authority.

Questions and answers

How high must a stair balustrade be in Germany?

Rail height on stairs: 900 mm (drop 1–12 m); 1100 mm (drop over 12 m). Rail height on landings and balconies: The same; 1000 mm in workplaces (e.g. Hesse).

What is the maximum opening in stair guarding in Germany?

Max opening in guarding: ≤ 120 mm in at least one direction (e.g. Berlin § 38); Baden-Württemberg: horizontal gaps ≤ 20 mm up to 600 mm height. Climbability: Climbing must be made difficult (vertical bars, a closed panel up to 700 mm, etc.).

When does a stair need a landing in Germany?

Landings: After at most 18 risers (DIN 18065; not in buildings with up to 2 dwellings).